Describe a real working day
Give the supplier the work pattern, expected intensity, breaks and shift length. Ask how the proposed unit's operating time depends on that duty and on site conditions. A brochure maximum is not a guarantee for your application. Explain whether the machine can stop mid-shift or whether another unit would be needed while it charges.
Verify the supply before delivery
Ask for the charging equipment and supply requirements of the exact unit. Have an appropriately qualified electrical person confirm that the site's available supply and installation are suitable. Identify who supplies the charger and associated equipment. A power point somewhere on the site does not establish that the complete charging arrangement is ready for the machine.
Protect the charging window
Allocate a practical parking and charging location that remains accessible after the working day. Discuss cable routing, security and the site's charging rules with the responsible team. Nominate who connects the unit according to its instructions and checks readiness for the next shift. If multiple machines share infrastructure, schedule them rather than assuming they can all charge together.
Compare the whole arrangement
Include charging infrastructure, transport, standby equipment and support in the quote comparison. Ask how the supplier handles charging faults and whether a replacement includes a compatible charger. Record the supplied accessories at handover and return. If site power is unavailable, have the supplier assess alternatives; adding another hired power source can change the cost and practical benefits of the choice.
Put it into a practical brief
For an electric access platform used over consecutive shifts, give the supplier both shifts' duty and the charging window between them. Ask who provides the charger and what site supply must be confirmed. If another machine shares the charging area, disclose that arrangement to the people assessing capacity and scheduling. Nominate an end-of-shift contact to follow the manufacturer's charging process and report faults. Check readiness before the next crew arrives, so an incomplete charge is discovered while there is still time to arrange support.
Can an electric machine complete the planned shift?
Ask about the actual duty cycle, battery configuration and charging opportunity. A generic runtime claim cannot predict a different site's workload.
| Decision | Information needed | Next step |
|---|---|---|
| Work pattern | Active work, travel and breaks | Describe attachments and the expected intensity of use. |
| Charging | Supply, charger and parking location | Have the required electrical arrangements confirmed. |
| Contingency | Delayed charge or longer shift | Agree who authorises a replacement or programme change. |
A worked planning example
An indoor fit-out needs equipment across two shifts. Overnight charging is not available if the second shift uses the machine during that period. Explain both shifts to the supplier and ask for a charging plan tied to breaks, charger compatibility and the available supply. Confirm who provides the charger and who is responsible for the charging area. Compare the whole arrangement with other suitable options, including any additional machine needed while one charges. Do not quote an expected runtime to the work crew until the supplier has addressed the actual duty cycle.
Common mistakes to catch
- Treating battery runtime as a fixed number for every task.
- Booking the machine without its compatible charger.
- Assuming any site socket is suitable.
- Ignoring a second shift when planning overnight charging.
References for your enquiry
Official pages consulted on 24 September 2026. The examples above are original planning illustrations.
- Safe Work Australia: managing risks of plant ↗
Model guidance for plant-related risk management. Check the applicable state or territory requirements and the specific manufacturer's instructions.
Find relevant equipment
General guidance only. Confirm project-specific requirements with competent people and the proposed supplier.