Generator hire: build a useful load schedule

List what needs power, when it runs and what happens if supply stops. Let the supplier and electrical specialist size the system from that brief.

By Plant Hire Directory · Editorial approach

Expanded with a decision table and planning example · Updated

List actual equipment

Record equipment names, nameplate information and whether items run together or at different times. Include starting loads where known and identify anything that must remain on continuously. Supply photographs of plates if you are unsure how to interpret them. Ask the generator supplier and appropriately qualified electrical person to establish the required system; adding headline wattages is not a complete sizing exercise.

Describe the distribution

Show the proposed generator position and the locations requiring power. Explain cable routes, vehicle crossings and the distance to site facilities. Ask who supplies distribution equipment, cables and any required connection work. Clarify what is included in the hire package so the generator does not arrive without the equipment or authorised people needed to make the system usable.

Plan fuel and attendance

Tell the supplier the expected operating hours and access windows for servicing or refuelling. Ask for fuel-use assumptions for the proposed duty, tank arrangements and monitoring options. Identify who checks the system and who receives an alert or reports a fault. For overnight operation, discuss site security, noise constraints and how support staff can gain access if needed.

Decide what an interruption means

Explain which activities can pause and which require a continuity plan. Ask the supplier to price any backup arrangement separately with its actual changeover scope. Compare delivery, fuel service, distribution and support alongside the base machine rate. At return, retain hour and fuel records and agree who disconnects and collects each part of the package.

Put it into a practical brief

For a temporary site compound, list the individual facilities and equipment rather than asking for a generator for a certain number of workers. Identify which loads start together, which continue overnight and which are essential to the next shift. Send the list to the supplier and electrical specialist for assessment. Ask for the proposed generator, distribution and fuel-service scope to be shown separately. If the compound expands, revisit the load schedule before adding equipment; the original hire package was assessed against the earlier duty, not every future addition.

The decision desk

What belongs in the load schedule?

List each load, how it starts, when it operates and the connection it needs. Give the supplier information to assess the system rather than selecting a generator from a rough total.

What to compare before booking
DecisionInformation neededNext step
Continuous loadsRatings and simultaneous useIdentify what runs throughout the shift.
Intermittent loadsStarting behaviour and sequenceMark equipment that starts together.
Site systemDistribution, cables and environmentAllocate electrical installation responsibilities.

A worked planning example

A hypothetical temporary workshop runs lighting, tools and a compressor. The compressor starts intermittently while other equipment remains on. Send nameplate information and the work pattern rather than only a summed power figure. Ask the supplier to propose the generator and distribution arrangement, and have the required electrical work assessed by the responsible qualified person. Confirm refuelling access, expected run hours and what happens if an extra machine is added. Keep a revised load schedule with any change to the system.

Common mistakes to catch

  • Ignoring starting loads.
  • Leaving cable and distribution costs out of the quote.
  • Assuming every outlet or site connection is suitable.
Put this into your enquiry brief →

References for your enquiry

Official pages consulted on 24 September 2026. The examples above are original planning illustrations.

Find relevant equipment

General guidance only. Confirm project-specific requirements with competent people and the proposed supplier.

Questions, answered

Putting this guide to work

Can I size the generator by adding wattage labels?

That is not a complete assessment. Starting behaviour, simultaneous loads and the installation matter; have the supplier and responsible electrical professional assess the requirement.

What if the load changes during hire?

Update the schedule and obtain confirmation before connecting additional equipment. Do not assume spare capacity from the original headline rating.