By Plant Hire Directory · Editorial approach
Expanded with a decision table and planning example · Updated
Identify the decision points
Ask the project team which conditions prevent delivery, site access or the planned work. Operating limits must come from the relevant equipment instructions and competent site assessment. Keep commercial decisions separate: a machine being unable to work does not automatically establish that hire charges stop. Nominate who makes the site decision and who informs the supplier.
Ask for the applicable terms
Request the supplier's postponement and cancellation notice requirements, standby basis and extension process in writing. Clarify whether operator travel, reserved transport or already-dispatched equipment are treated separately. There is no single weather policy shared by every hire company. Compare the actual offers against the same possible interruption rather than assuming one supplier's practice applies to another.
Plan the restart and exit
After a delay, access or ground conditions may have changed even if the weather improves. Arrange the necessary site reassessment and tell the supplier about changes before confirming a new delivery or collection. Consider whether another job has priority for the machine after the original booking. An extension request should be acknowledged, not inferred from the equipment remaining on site.
Keep a simple decision record
Record the time, person contacted, decision and written acknowledgement for each change. Refer to current Bureau of Meteorology warnings and relevant road-authority updates rather than a directory's static regional description. Retain the revised programme with the hire record so invoices can be checked against what was agreed. This is particularly useful when several machines or transport bookings move together.
Put it into a practical brief
For an earthworks package with a booked float, ask when the dispatch team needs a go-or-postpone decision. Give that time to the person assessing site readiness. If access is not suitable, document the decision and obtain the supplier's response before assuming the booking has moved. Separately discuss any operator or transport already committed. When the project restarts, confirm the machine is still available and the access route has been reassessed. A weather postponement is a programme change involving several responsibilities, not simply a different start date.
Who can change the booking when conditions deteriorate?
Agree a decision maker, notification process and commercial treatment before dispatch. A forecast alone does not explain what the contract charges.
| Decision | Information needed | Next step |
|---|---|---|
| Before delivery | Readiness and cancellation cut-off | Nominate who can postpone dispatch. |
| On site | Standby and extension terms | Ask how charges change when work stops. |
| Collection | Access and security | Agree responsibilities if removal is delayed. |
A worked planning example
A hypothetical outdoor job faces a forecast change before the machine leaves the depot. The site team needs to decide whether to proceed, postpone or change the programme. Ask the supplier what notice is required and whether transport has already been committed. Keep the decision in writing with the revised delivery date. If equipment is already on site, check standby, security and collection arrangements separately. Do not assume the supplier stops charging because the work cannot proceed; resolve the applicable terms before they become a dispute.
Common mistakes to catch
- Waiting until the float arrives to report an unready site.
- Assuming weather automatically cancels hire charges.
- Forgetting collection access in the postponement plan.
References for your enquiry
Official pages consulted on 24 September 2026. The examples above are original planning illustrations.
- Kennards Hire: contract conditions ↗
An example supplier contract to consult when checking hire responsibilities. These terms do not apply to other suppliers by default.
- Coates: terms of hire ↗
A second supplier's published terms. Read the actual offer and applicable conditions for your booking.
Useful primary sources
Find relevant equipment
General guidance only. Confirm project-specific requirements with competent people and the proposed supplier.
