Put every offer on the same footing
Start by separating the machine rate from mobilisation, demobilisation, operator costs, fuel, attachments, cleaning, damage waivers and any minimum hire period. Ask whether the quoted day means a calendar day, a shift or a stated number of engine hours. A useful comparison shows the likely whole-of-job cost, not simply the most prominent rate.
Test the assumptions behind the number
Confirm the machine class, model or equivalent, operating weight, included attachments and where the unit will travel from. For operated hire, check ordinary hours, overtime, travel and accommodation. For dry hire, establish who carries daily checks, refuelling, greasing, security and return condition responsibilities.
Leave a clean record
Record clarifications in writing and attach the final scope to the purchase order. List the delivery window, site contact, access constraints, induction requirements and cancellation conditions. This gives the supplier a better chance of sending the correct combination and gives the project team a reliable baseline when circumstances change.
Which quote is actually cheaper?
Compare the same work period and configuration, then add every required cost. An unspecified inclusion is a question to resolve, not a zero in your spreadsheet.
| Decision | Information needed | Next step |
|---|---|---|
| Hire period | Daily, weekly and engine-hour limits | Ask how weekends, overtime and minimum hire interact. |
| Mobilisation | Delivery and collection separately | Confirm the source depot and whether waiting is chargeable. |
| Risk and support | Damage terms, breakdowns and standby | Compare the written obligations as well as the amount payable. |
A worked planning example
Illustrative comparison: an excavator offered at $250 per day for three days with $360 return transport totals $1,110. A second offer at $290 per day with $200 return transport totals $1,070. The higher daily rate is $40 lower overall. That result holds only if the machine, attachments, working allowance and tax basis match. If one offer includes a required attachment and the other does not, price it before making the decision. These figures demonstrate arithmetic; they are not Australian market rates.
Common mistakes to catch
- Comparing one GST-inclusive price with one GST-exclusive price.
- Treating an empty transport line as included delivery.
- Using planned workdays where the contract charges calendar days.
- Comparing different machines without checking the required task.
References for your enquiry
Official pages consulted on 24 September 2026. The examples above are original planning illustrations.
- Kennards Hire: contract conditions ↗
An example supplier contract to consult when checking hire responsibilities. These terms do not apply to other suppliers by default.
- Coates: terms of hire ↗
A second supplier's published terms. Read the actual offer and applicable conditions for your booking.
General guidance only. Confirm project-specific requirements with competent people and the proposed supplier.